I-64 Capacity Improvements Segment I
Virginia DOT

The discovery of soil conditions that would impact the design as originally conceived, among other factors, led the design-build team to convince the owner that replacing the existing bridges rather than rehabilitating them would be better. By lengthening the bridge spans to avoid the problematical soils, the team was able to produce a new design that in the end reduced overall costs and met the established deadlines.