Children’s Health initiated the Specialty Center Fairview project to expand access to pediatric specialty care for families in the growing North Dallas region. Anchored by the Children’s Health Andrews Institute for Orthopedics & Sports Medicine, the facility accommodates multiple pediatric specialties, including cardiology, neurology, gastroenterology and pulmonology.
Located on the first floor of an existing leased office building, the project required flexible clinical spaces that could accommodate rotating providers while maintaining efficient patient flow and high-quality care. An already aggressive 16-month schedule was further compressed when the Owner requested accelerated delivery midway through construction.
The clinic combines durable, high-quality finishes with a welcoming environment designed specifically for children and families. Patient privacy, security and intuitive wayfinding were integrated throughout. By balancing speed, cost control and operational flexibility, the project creates an adaptable healthcare setting that meets growing community needs while supporting Children’s Health’s long-term expansion.
Winner – Best in Small Projects – Vertical
Faced with an accelerated schedule, the Children’s Health Fairview Clinic team delivered six months ahead of its original completion date and more than $1.36 million below the initial contract price. Those results began with a selection process focused on transparency, cost and team chemistry, then carried into delivery through close collaboration and rapid decision-making. The project shows that small scale doesn’t mean small results when the right design-build team is aligned from the start.
“From an Owner’s perspective, the Children’s Hospital went out of their way to meet and exceed expectations in both cost and time.” — Awards Jury
Design-Build Team
| Client/Owner: | Children’s Health |
| Owner Advisor: | SPMT |
| Design-Builder: | The Beck Group |
| Architect: | The Beck Group |
| Engineers: | L.A. Fuess Partners; SSR Inc. |
| Specialty Contractor: | HSG, Inc. |
| Project Cost: | $10,867,526 |
| Construction Duration: | 10 months |