Challenge Design-Build Project Delivery Addressed
To address long-term drought conditions and solve water supply challenges for two California cities, the Davis-Woodland Water Supply Project highlights how design-build delivery achieved significant capital savings, cost certainty, and 20 years of guaranteed water treatment and operations staff for the Woodland-Davis Clean Water Agency.
Summary
A regional project helping solve the long-term water needs of two California cities, the Davis-Woodland Water Supply Project highlights how design-build delivery design-build delivery achieved significant capital savings and cost certainty for the Woodland-Davis Clean Water Agency. CH2M worked with the Agency to develop a true design-build partnership and balanced risk approach to achieve significant capital savings and cost certainty. The project, completed in 2016, provides a needed water resource to mitigate severe drought conditions.
Design-Build Team
Client/Owner: Woodland-Davis Clean Water Agency
Design-Builder: CH2M
General Contractor: CH2M
Architect: CH2M
Engineer: CH2M
Specialty Contractors: Overaa Construction, San Joaquin Electric
Specialty Consultants: Cunningham Engineering, Betty Woo Architects
Duration of Construction: 25 months
Project Cost: $145,651,145