For its first design-build project, Georgetown University took a bold approach to transforming a 12-story, 400,000-sq.-ft. office building into an academic hub for its growing Capital Campus. Located in Georgetown’s historic district and known locally as the “Darth Vader Building,” the aging 1980s structure presented significant renovation challenges and an immovable August 2025 academic deadline.
Rather than pursuing a traditional procurement, Georgetown directly selected its design-build partner for the nearly $200 million project, embracing Progressive Design-Build to manage risk, maintain budget transparency and accelerate delivery. Five DBIA Certified Professionals contributed their expertise as the team transformed the building into flexible classrooms, lecture halls, laboratories, student gathering spaces and community amenities.
The renovation also improved pedestrian access and public spaces while preserving the building’s distinctive character. Through early collaboration and disciplined decision-making, Georgetown turned a complex first-time design-build undertaking into a cornerstone of its expanded Capital Campus.
Winner – I.N.S.P.I.R.E.D. Owner
(Innovative Newcomer Showcasing Preparedness, Insight, Readiness and Enduring Diligence)
Some first-time Owners dip their toe into design-build. Georgetown University jumped in with both feet. Facing an immovable academic deadline, Georgetown prepared through DBIA training and an experienced Owner Advisor, then embraced a true “one team” approach to Progressive Design-Build. In just over two years, the team transformed a complex 1980s high-rise into an anchor of Georgetown’s Capital Campus. The experience proved so successful that Georgetown is pursuing design-build on future campus projects.
“Some people dip their toe into design-build. This first-time Owner jumped in with both feet.” — Awards Jury
Design-Build Team
| Client/Owner: | Georgetown University |
| Owner Advisor: | Thomas Group Consulting LLC |
| Design-Builder: | The Whiting-Turner Contracting Company |
| Architect: | SmithGroup |
| Engineer: | SmithGroup |
| Specialty Contractor: | F.B. Harding, Inc. Electrical Contractors |
| Project Cost: | $183,129,977 |
| Construction Duration: | 26 months |
Photos



Photo Credits: Edward Caruso Photography