Piscataway WRRF Bioenergy Project

2026 | I.N.S.P.I.R.E.D. Owner | Water / Wastewater
Accokeek, MD

Design-Build Team Summary

The Piscataway Water Resource Recovery Facility (WRRF) Bioenergy Project represents the most technically advanced undertaking in WSSC Water’s 106-year history and its first use of design-build delivery. Recognizing the complexity, WSSC embraced a collaborative approach that allowed the team to refine solutions throughout design and construction.

One of only seven facilities nationwide incorporating thermal hydrolysis, the project centralizes biosolids treatment from WSSC’s six regional facilities, producing higher-quality Class A biosolids while recovering renewable energy.

Early collaboration led to improvements beyond the original project requirements, including prefabrication strategies to address labor and material shortages and redundant equipment to reduce operational downtime.

The facility is projected to generate $4 million annually through renewable energy sales and save customers $3.4 million annually through reduced biosolids volume and disposal costs. By combining advanced technology with collaborative decision-making, WSSC delivered a more efficient, sustainable facility designed for long-term operational performance.

Winner – I.N.S.P.I.R.E.D. Owner

(Innovative Newcomer Showcasing Preparedness, Insight, Readiness and Enduring Diligence)

Before taking on its first design-build project, WSSC Water made sure it was ready. Through training, experienced advisors and a procurement strategy built around collaboration and shared risk, WSSC prepared its team to take an active role in PDB. They stayed engaged, trusted the expertise around the table, and empowered the team to make decisions together, helping deliver a first-of-its-kind bioenergy facility that sets a standard for wastewater treatment.

“They built organizational readiness and created a culture aligned with design-build best practices.” — Awards Jury

Design-Build Team

Client/Owner:WSSC Water
Owner Advisor:HDR
Design-Builder:PC Construction
General Contractor:PC Construction
Engineers:Stantec; Hazen and Sawyer
Specialty Contractors:Albrecht Engineering, Inc.; CSA Central, Inc.; EPCM, Inc.; Milhouse Engineering & Construction, Inc.; SP Arch Inc.
Project Cost:$269,000,000
Construction Duration:61 months

Photos

Photo Credits: Multivista