Resources Building Renovation

2026 | Rehabilitation/Renovation/Restoration | Enlightened Owner | National Award of Excellence | National Award of Merit
Sacramento, CA

Design-Build Team Summary

Winner – Merit and Excellence in Rehabilitation/Renovation/Restoration

The California Department of General Services (DGS) once ranked Sacramento’s 17-story Resources Building as the worst-performing property in its statewide portfolio. The 1960s high-rise suffered from seismic deficiencies, outdated infrastructure and hazardous materials that complicated nearly every intervention. DGS chose rehabilitation over demolition, preserving the structural frame while creating a resilient workplace for more than 2,500 employees.

As one of California’s earliest Progressive Design-Build (PDB) projects, the renovation required DGS to take an active role. Owner decision-makers and advisors worked in the Big Room, participating directly in design development, procurement and open-book cost reviews. Fee proposals remained sealed until the preferred team was selected, keeping the qualifications-based process focused on capability and collaboration.

Investigation Replaces Assumptions with Certainty

PDB allowed the team to investigate the building before establishing the Guaranteed Maximum Price (GMP). With DGS authorization, crews removed exterior panels, exposed structural connections and explored foundations. Those investigations replaced conservative assumptions with verified conditions and eliminated approximately two months of schedule uncertainty. The team established a $436 million GMP within 140 days of notice to proceed, with approximately 80% of the project already bought out.

Early regulatory participation provided similar certainty. The Office of the State Fire Marshal joined recurring implementation meetings, contributing to a first-pass approval rate above 90% across approximately 23,000 inspections.

The completed building incorporates 128 fluid viscous dampers to strengthen seismic performance while preserving usable space. Reusing the structure reduced embodied carbon by 61%. Although the project originally targeted LEED Silver, it achieved LEED Platinum and exceeded California’s Title 24 energy requirements by more than 21%.

The final cost reached $480 million after DGS added scope and enhancements beyond the original GMP. Even with the expanded program, the team achieved all nine project goals and received its Certificate of Occupancy 67 days early. A formerly inaccessible 15,000-sq.-ft. plaza now provides new public space in downtown Sacramento.

Winner – Enlightened Owner

California had a bold vision for its worst-performing office building: take it from “Worst to First.” DGS chose Progressive Design-Build to tackle the uncertainty of a complex seismic retrofit and renovation, then stayed actively engaged as the team investigated conditions, managed risk and made decisions together. That Owner leadership paid off. The team finished the project 67 days early, cut embodied carbon by 61% and achieved LEED Platinum on a Silver budget. DGS knew what success looked like and gave its team the conditions to deliver it.

“From the beginning, the Owner established a clear vision for success, and the design-build team rallied around ‘Worst to First’ as the project’s North Star.” — Awards Jury

Design-Build Team

Client/Owner:California Department of General Services
Owner Advisor:Gilbane-Cypress Construction Management
Design-Builder:Turner Construction Company
General Contractor:Turner Construction Company
Architects:AC Martin; HGA
Engineers:Buehler Engineering; Redwood Electric; Southland Industries
Specialty Contractors:Glumac; Walters & Wolf; Silverado Contractors; RSC Engineering, Inc.; Harris Hoisting
Project Cost:$480,000,000
Construction Duration:36 months