SCDOT Bridge Package 29 – Oconee US 76 & Jasper US 278

2026 | Crisis/Emergency Repair | Transportation
Oconee & Jasper Counties, SC

Design-Build Team Summary

SCDOT Bridge Package 29 restored two critical South Carolina crossings washed out by Hurricane Helene, reconnecting communities and reducing lengthy detours that disrupted daily travel and commerce. The emergency design-build project replaced the US 76 bridge in Oconee County and the US 278 culvert in Jasper County with new, resilient bridge structures.

With sites more than three hours apart, the team relied on close coordination and accelerated design, permitting and construction to meet SCDOT’s urgent schedule. At US 76, crews also managed a damaged waterline and demolished a structurally unsound 1928 bridge that obstructed river flow.

Despite holiday schedules, inclement weather and complex site conditions, the team delivered construction-ready drawings within five weeks and relocated utilities within 10 weeks of award. Both crossings were completed in approximately six months, ahead of schedule and under budget, restoring essential transportation connections for residents, businesses and surrounding communities.

Winner – Crisis/Emergency Repair

After Hurricane Helene washed out two critical South Carolina crossings, SCDOT turned to emergency design-build to restore mobility fast. Design, permitting, procurement and construction progressed concurrently across sites more than three hours apart, while crews tackled damaged utilities and a structurally unsound 1928 bridge. What resulted was US 278 reopening in 169 days and US 76 in 220, restoring vital connections ahead of schedule and under budget.

“With detours up to 76 miles, SCDOT had to move fast, but it still preserved competition through proprietary meetings with three teams and delivered design-build the right way.” — Awards Jury

Design-Build Team

Client/Owner:South Carolina Department of Transportation
Design-Builder:Crowder Construction Company
General Contractor:Crowder Construction Company
Engineer:Infrastructure Consulting & Engineering, LLC
Project Cost:$15,358,174
Construction Duration:6 months

Photos