Winner – Merit and Excellence in Aviation
San Francisco International Airport’s (SFO) Harvey Milk Terminal 1 replaces an aging facility with a terminal designed around operational resilience, environmental performance and an inclusive passenger experience. The project required full demolition and reconstruction while airline, TSA, baggage and passenger operations continued around it. Multiple phased turnovers kept the airport functioning throughout nearly a decade of work.
Progressive Design-Build (PDB) was essential to managing that complexity. When the project evolved from a renovation into a full replacement, early collaboration allowed SFO and the design-build team to redefine the scope, develop a workable phasing strategy and maintain budget alignment through open-book cost development.
One Team Across Interconnected Projects
The team also coordinated closely with the separately contracted Boarding Area B project. A shared Big Room brought both design-build teams together with SFO to align systems, resolve field conflicts and jointly procure several major building components. More than 90 formal partnering sessions sustained the project’s “One Team, One Project” culture. That collaboration is estimated to have avoided approximately $38 million in potential costs.
The same structure supported recovery from unforeseen conditions. Hazardous materials threatened approximately 40 workdays, but Lean planning and coordinated resequencing regained the lost time without affecting the final schedule. The terminal opened on time and below its Guaranteed Maximum Price (GMP).
Harvey Milk Terminal 1 is the world’s first airport terminal to achieve both LEED v4 Platinum and Fitwel certification. It reduced embodied carbon by more than 25% and diverted more than 90% of construction waste from landfills. The project also exceeded SFO’s Local Business Enterprise participation goals, directing more than $186 million to certified local firms.
As the world’s first airport terminal named for an openly LGBTQ+ leader, the facility also advances inclusion in public infrastructure. It includes the nation’s first all-gender airport restroom, a sensory room for neurodivergent travelers and a permanent exhibit honoring Harvey Milk’s life and legacy.
Winner – Project of the Year
Over nearly a decade, SFO and its design-build partners transformed an operating terminal through exceptional collaboration, design excellence, technology and problem-solving. The team navigated hazardous materials, complex phasing and evolving conditions while keeping passengers, airlines and baggage operations moving. When one challenge threatened the schedule, they recovered 40 lost workdays; when an existing pedestrian bridge conflicted with the new terminal, they raised the 320,000-pound structure nearly 5 feet rather than replace it. Through it all, the team never lost sight of the passenger experience, sustainability or community the terminal represents. Delivered on time and below GMP, Harvey Milk Terminal 1 is both a civic landmark and a powerful example of what an integrated design-build team can achieve together.
“It feels less like an airport terminal and more like a civic landmark: elegant, calm and designed to take some of the stress out of travel.” — Awards Jury
Winner – Best in Design – Architecture
Progressive Design-Build helped turn Harvey Milk Terminal 1 into an airport experience shaped as much by design as by function. Sweeping forms, skylights and integrated art create a sense of place rooted in San Francisco, while intuitive wayfinding and a quiet-terminal approach bring a sense of calm to the passenger journey. Sensory rooms and other inclusive spaces extend that thoughtful design to travelers with different needs. The result is an elegant civic gateway where architecture, accessibility and passenger experience work together with purpose.
“The art integration, spatial clarity and use of natural daylight all work together to create an exceptional passenger experience. This terminal is elegant!” — Awards Jury
Winner – Best in Leadership/Teaming
“One Team, One Project” was more than a motto. More than 90 partnering sessions brought stakeholders together across a program that included two design-build teams working concurrently. That commitment carried beyond construction to local businesses, workforce development and the surrounding community. The project intentionally made teaming a strategic priority, a decision that was critical to its success.
“This project intentionally made teaming a strategic priority and that was critical to the project’s results. The airport from top to bottom is a top-notch project.” — Awards Jury
Design-Build Team
| Client/Owner: | San Francisco International Airport |
| Owner Advisor: | ACJV, a joint venture of AECOM and Consor PMCM, Inc. |
| Design-Builder: | Hensel Phelps Construction Co. |
| General Contractor: | Hensel Phelps Construction Co. |
| Architects: | Gensler; Kuth Ranieri Architects |
| Engineers: | Critchfield Mechanical; Redwood Electric Group; BEUMER Corporation |
| Specialty Contractors: | Rosendin Electric; Transbay Fire Protection; MKA; Meyers+ Engineers; MEI |
| Project Cost: | $1,530,000,000 |
| Construction Duration: | 109 months |
Photos



Photo Credits: Jason O’Rear